Roundhouse Work Session Report for – September 10th, 2016

By | News, Progress | No Comments

Work Report

The work session today was single minded and to the point.  Our efforts were put toward lapping in the main throttle valves and putting the throttle back together.  All throttle stud threads were chased and cleaned.  The copper gaskets were fitted and secured in place to the throttle heads with ultra copper.  Work still needs to be done on the lapping process so this task has not been completed.  It will continue at the next work session.  The throttle linkage was installed on the engine ready for testing. Read More

Remains of the Reading

By | Fire Up 2100, News, Video | No Comments

The Reading Company once maintained one of the largest railroad shops in the world and employed thousands in eastern Pennsylvania. Remarkably, the Reading shops still stand and have been adapted for other uses, but even more remarkable is this: one of the Company’s massive steam locomotives has survived and is now undergoing restoration.

DONATE

December 2015 Work Session

By | Progress | No Comments

Reading 2100 shirts on their way!

By | Uncategorized | No Comments

Show your support of the American Steam Railroad with these stylish Reading 2100 shirts! With a style influenced by the Reading Railroad’s late era marketing, these shirts are some of the most attractive railroad wares around.

These shirts will be available to order online for $15.00 on November 30th.

Email us to let us know if you’re interested in ordering.

October Work Session

By | Fire Up 2100, News | No Comments

The American Steam Railroad hosted another volunteer work session on October 31st. With a dozen volunteers on hand, the following work was performed:

  • Cleaned smoke box of sand and soot from previous.
  • Replaced improperly installed washout plug on the throat sheet.
  • Continued drilling out stay-bolt tail tell holes inside the firebox and syphons.  Evidence shows that this work was not regularly performed during the engine’s last service life. This will help us get ready for the hydrostatic test.
  • Started needle scaling the outside of the boiler to make way for proper boiler protective painting with a boiler paint to stop rusting and protect the boiler for the long haul.
  • Washout plugs removed for inspection of the mud ring and boiler shell for inspection.

The next scheduled work session is November 21st and 22nd. Crews will be continue preparing for the hydrostatic test in addition to a potential fire-up.